Business |
Factory |
Role |
Operating plan |
Motorcycle |
Iwata Main |
Assembly of finished products and engines |
March 28: Limited production March 29-April 1: Production suspended |
Iwata South |
Assembly of engines |
Hamakita |
Manufacture of parts |
March 28-April 1: Limited production for overseas model parts |
Morimachi |
Nakaze |
Fukuroi |
Packaging for overseas model parts |
March 28-April 1: Operation will continue |
Outboard Motors |
Fukuroi South |
Assembly of finished products |
March 28-April 1: Production suspended |
YKP* |
PWC* |
Kuramatsu |
Assembly of engines |
March 28-April 1: Production suspended |
Automobile Engines |
Iwata main |
Assembly of engines |
March 28-April 1: Production suspended |
Power Products |
YMPC* |
ATV* |
March 28: Limited production March 29-April 1: Production suspended |
Golf Car |
March 28-30: Limited production March 31-April 1: Production suspended |
Generator |
March 28-March 31: Limited production April 1: Decision pending |