Business |
Factory |
Role |
Operating plan |
Motorcycle |
Iwata Main |
Assembly of finished products and engines |
March 24-25: Assembling partially complete units from stocked parts supplies |
Iwata South |
Assembly of engines |
Hamakita |
Manufacture of parts |
24-25: Limited production for overseas model parts |
Morimachi |
Nakaze |
Fukuroi |
Packaging for overseas model parts |
24-25: Operation will continue |
Outboard Motors |
Fukuroi South |
Assembly of finished products |
24: Assembling partially complete units from stocked parts supplies 25: Production suspended |
YKP |
24: Production suspended 25: Assembling partially complete units from stocked parts supplies |
PWC* |
Kuramatsu |
Assembly of engines |
24-25: Assembling partially complete units from stocked parts supplies |
Automobile Engines |
Iwata main |
Assembly of engines |
24-25: Production suspended |
Power Products |
YMPC |
ATV* |
24-25 Assembling partially complete units from stocked parts supplies |
Golf Car |
24-25: Production suspended |
Generator |
24-25: Limited production |